February was a funny month.  Plagued by rain, including several thunderstorms which dumped vast quantities of water on the site in the space of half and hour or less, progress was slower than expected.  Here is a quick photographic update of where we are now on the 1st of March.  I’d like to believe that the dry, more mellow days of Autumn are around the corner, but if the steady rain today is anything to go by, that would be foolishly optimistic.

Albert, our head builder.

Albert, our head builder.

Albert is on site everyday and participates in the weekly site meetings.  He seems to manage and co-ordinate all the other workers quietly and without fuss.

Rupert, our site manager.

Rupert, our site manager.

Rupert is often on the site but also takes care of small collections and deliveries of materials.

Fireplace in the making.

Fireplace in the making.

The fireplace is going on the west wall of the living room with a sash window on either side.

Consulting.

Consulting.

A makeshift table.

A makeshift table.

Windows between lower and upper kitchen cupboards.

Windows between lower and upper kitchen cupboards.

These windows will be able to be opened.  The eastern boundary wall is very close to the kitchen so I’m on the lookout for interesting garden wall features.

Concrete lintels for the first floor have arrived.

Concrete lintels for the first floor have arrived.

The first floor slab is made up of concrete lintels with blocks that interlock with them in some way.  Other than in the garage, on the ground floor we are having plastered ceilings below the slab.

My brother (an architect), and my sister-in-law (with an eye for design) from Cape Town doing an impromptu site inspection.

My brother (an architect), and my sister-in-law (with an eye for design) from Cape Town doing an impromptu site inspection.

Retaining wall going up on North side of cottage.

Retaining wall going up on North side of cottage.

The retaining wall which is being built down the west side and across north side of the cottage is one feature that has been altered during the construction process.  The engineer decided it should be a double core wall.  This comprises two identical walls built parallel to each other.  The space between the two wall is filled with concrete and a special, porous waterproof membrane in incorporated to diffuse water rather than have it build up against the brickwork.  Looking at the work in progress one could be forgiven to thinking we were building a fort.  Hopefully all this extra effort will prevent the cottage from sliding down onto the house below – even if this rain never stops.

Lintels ready to be raised into position.

Lintels ready to be raised into position.

In South African brick-built houses,the  first floor is often made up of concrete lintels interlocked with blocks.  Sometimes the ceiling of the ground floor is simply the plastered, painting underside of these lintels.  In our case, we’re putting in plastered ceiling board 150mm below the slab.  Electrical wiring, transformers for downlights etc can then be fitted between the slab and the ceiling board.  This allows for changes to be made later too if you decide you need more fittings at a later stage.

Concrete lintels in place above garage. February 27th.

Concrete lintels in place above garage. February 27th.

Almost each time I visit the site, I find some sort of random ‘still life’ arrangement that looks like a painting waiting to happen.  Below is an example:

Boots made for Working.

Boots made for Working.

And I love the way every effort is made to keep clothes tidy in the simplest of ways:

Hanging Space!

Hanging Space!

Hopefully the garage will soon be able to be used for storage and for keeping clothes and building materials dry.  When is this rain going to stop?  I’m thinking of buying gumboots.